In April 2019 our company started with the work for a replacement of the Stössingbach bridge - railway bridge over the Michlbach in Böheimkirchen. We manufactured steel beams included their railing with a range of 7,46 meters, which now replace the old steel beams from 1947. For the lifting part the railway was closed single-tracked over three weeks, the bridge parts were lifted by a crawler cran.

 


Rubrik:
bridge building
Leistungsumfang:

manufacturing and delivering of steel beams with a range from 7,46m

incl. railing

 

Lifting with a crawler crane

Kunde:
Porr Bau GmbH
Bauherr:
ARGE ÖBB Stössingbachbrücke
Ausführungszeit:
april till november 2019