Hail Aljouf
In March 2015 NCA was needed for constructing the steel construction of a transformer boiler plant. The whole construction had more than 45 tons, the heaviest part was the boiler with 17 tons. In our contract was not only the construction of steel parts but also the pipeworks and the preassembly.
Rubrik:
Power engineering
Leistungsumfang:
Construction of the whole steel structur for one power transformer incl. transport
Kunde:
Siemens AG - Nürnberg
Bauherr:
Siemens AG - Nürnberg
Architekt/Planer:
Siemens AG - Nürnberg
Ausführungszeit:
3 month
Eckdaten:
Weight: 45 ton; Material: S235JR+AR - S355J2+N, 1.4301 - 1.4571; Thickness: 1 - 60 mm