BAKU CONVENTION CENTER

In 2014 NCA got the biggest order of the companies history - the Convention Center in Aserbaidschan.

Almost 5000 tons steel and the related roof- and facade construction were a big challenge that needed to be mastered. 

2020 honored with the Meetings Star Award in the nomination category "Best Congress Centers in New Europe".

https://www.linkedin.com/posts/baku-convention-center_meetings-star-award-2020-best-convention-activity-6758269011521363968-MB00

https://www.linkedin.com/posts/baku-convention-center_worldarchitectureday-bakucongress-bakucc-activity-6850784367355265024-9Liz


Rubrik:
Special Highlights
Leistungsumfang:

Detailed design, structual design and calculation, engineering, manufactoring, delivery and installation

11.000 m2 glas facade

20.000 m2 standing seam roof

37.000 m2 second skin layer facade with perforated aluminium panels

57.000 m2 C3 painting system

incl. all secondery structures and conections

Kunde:
State committee on property issues of the republic of Azerbaijan
Bauherr:
ILK INSAAT SANAYI VE TICARET A.S.
Architekt/Planer:
State committee on property issues of the republic of Azerbaijan
Ausführungszeit:
12 month
Eckdaten:
Weight: 6000 tons; Material: S355J2+N; Thickness: 10 - 80 mm