Mayereinöd bridge

In autumn 2017, as part of the flood protection measures along the Salzach, we received the order to build a new bridge near Mayereinöd in Salzburg.

The new building is a structure in composite construction. In the transverse direction prefabricated TT plates with external reinforcement were chosen to allow a large slenderness and fast construction time.

All steel parts as well as the reinforcement were manufactured in our factory and provided with the first corrosion protection.

The main carrier was transported in two parts, each 25m long, to the construction site and welded there.  The highlight, even for many spectators from the surrounding area, was the lifting of the 50m long beams by a 600-tonne crawler crane.


Rubrik:
bridge building
Leistungsumfang:

π-plates

total weight: 220 tons

span: 50 Meter

weight of steel construction: 100 tons

volume of reinforced concrete: 1000 m3

Kunde:
Steiner Bau GmbH
Bauherr:
Hochwasserschutz Zeller Becken
Ausführungszeit:
march 2018 till december 2018