Deutsch
English
  Hundsdorf 25, 9470 St. Paul/Lavanttal
+43 4357 3120-0

Lateral shift Railway bridge Hüttau

After completion of the road and the edge of the beam structures were cross-moved to end position.

For this, the bridges at km 13 984 and 14 642 were stored in special move slide and moved hydraulically over the abutment and lowered onto the bearings.

All work, the route was blocked only 2 weeks, the shunting of both bridges lasted 3 days.